Soil remediation project of a former coking plant in Beijing

发布时间:2021-8-18   浏览量:

Auxiliary project of 2022 Beijing WinterOlympic Games, an industrial heritage park to be built on site afterremediation.
Scale of TTZ: high risk contaminated soil 59802m3;
COCs: benzene, benzopyrene;
Remediation Time-frame:2018-2019;
Remediation Effect: 100% met RG, min. COCs removal rate 99.8%.

COCs

RG (mg/kg)

Benzene

51.6

Benzopyrene

6.2